A. All project stakeholders should attend requirements workshops
B. Retrospectives are only run at the end of a project
C. It is best if the Project Manager facilitates the project’s workshops
D. An independent facilitator will manage the structure of a facilitated workshop but not input to the content
MorganEnlightened
D. An independent facilitator will manage the structure of a facilitated workshop but not input to the content.
D. An independent facilitator will manage the structure of a facilitated workshop but not input to the content.