A. A shared understanding of how fast a Sprint must be done.
B. The optimum Work in Progress limit for each Sprint.
C. The number of Story Points a Team can finish in 1 Sprint.
D. The sum of all completed Sprint Backlog Items
MorganEnlightened
C. The number of Story Points a Team can finish in 1 Sprint. >> The velocity is the number of units of work completed in a certain interval.
C. The number of Story Points a Team can finish in 1 Sprint.
>> The velocity is the number of units of work completed in a certain interval.