Scrum allows for re-estimating tasks based on growing insight. Who is responsible for updating the estimates of the work during a Sprint?
[A] The Development Team
[B] The Scrum Master
[C] The most senior member of the Team
[D] The Product Owner
[A] The Development Team --> At any point in time in a Sprint, the total work remaining in the Sprint Backlog items can be summed. The Development Team tracks the total work remaining at least for every Daily Scrum if needed after a re-estimate of tasks to be done. Hence the estimates for the remRead more
[A] The Development Team
–>
At any point in time in a Sprint, the total work remaining in the Sprint Backlog items can be summed. The Development Team tracks the total work remaining at least for every Daily Scrum if needed after a re-estimate of tasks to be done.
Hence the estimates for the remaining work are updated on a daily basis. Note that Scrum does not consider the time spent working on Sprint Backlog Items. The work remaining and date are the only variables of interest.
See less