D. The team should agree on the length of the iteration (timebox), taking the size and the complexity of the project into consideration.
D. The team should agree on the length of the iteration (timebox), taking the size and the complexity of the project into consideration.
See less
What is the best forum to discuss this issue and find a resolution?
B. Scrum-of-Scrums. The Scrum-of-Scrums is a coordination meeting where dependencies and resolution of cross-team issues can be discussed.
B. Scrum-of-Scrums.
The Scrum-of-Scrums is a coordination meeting where dependencies and resolution of cross-team issues can be discussed.
See lessWhat artifact are they likely to use for this?
B. Definition of Done. Definition of Done is a well understood and clearly documented definition of items that must be established to mark a story (or iteration or project) to be done.
B. Definition of Done.
Definition of Done is a well understood and clearly documented definition of items that must be established to mark a story (or iteration or project) to be done.
See lessWhat is the best course of action for the Development Team?
B. Ask the Product Owner to decide which stories can be delayed until the next Sprint. The Product Owner should decide which items have the most value and should be done first in this Sprint.
B. Ask the Product Owner to decide which stories can be delayed until the next Sprint.
The Product Owner should decide which items have the most value and should be done first in this Sprint.
See lessRegarding the User Story in a Sprint, what must be small?
C. the Story Points or Ideal Hours involved. User Stories at the top of the Product Backlog, and thus Stories in the Sprint, have to be small. They need to be small to ensure that they fit into 1 Sprint and that they are defined precisely enough.
C. the Story Points or Ideal Hours involved.
User Stories at the top of the Product Backlog, and thus Stories in the Sprint, have to be small. They need to be small to ensure that they fit into 1 Sprint and that they are defined precisely enough.
See lessWhat should this role be called after the transition?
C. Scrum Master. The work of the Project Coordinator is similar to that of the Scrum Master. It's important in Scrum not to change the names for the different roles. This helps to keep Scrum working.
C. Scrum Master.
The work of the Project Coordinator is similar to that of the Scrum Master. It’s important in Scrum not to change the names for the different roles. This helps to keep Scrum working.
See lessHow should ’Done’ be defined when multiple Scrum Teams are working on a single product?
A. All Scrum Teams work towards an integrated Definition of Done. Using an integrated Definition of Done ensures that the pieces of the project will fit together and are in the same state of Done.
A. All Scrum Teams work towards an integrated Definition of Done.
Using an integrated Definition of Done ensures that the pieces of the project will fit together and are in the same state of Done.
See lessWho should be present when reviewing and adjusting the Sprint work?
C. The Development Team only. The Product Owner should be consulted. The Development Team itself has to make decisions about how to distribute the work. They need to redistribute the work amongst themselves. If the process needs guidance, they can ask the Scrum Master to guide the discussion. The PrRead more
C. The Development Team only. The Product Owner should be consulted.
The Development Team itself has to make decisions about how to distribute the work. They need to redistribute the work amongst themselves. If the process needs guidance, they can ask the Scrum Master to guide the discussion. The Product Owner needs to be consulted to ensure that tasks dropped have the lowest value for the customer.
See less