Which statement is true regarding this scenario?
B. Points are assigned for the Overall Story, not for parts of the Story. >> The Story should be estimated as a whole. Points for what a tester feels he needs plus what a developer feels he needs should not be given. Both should estimate the complete Story.
B. Points are assigned for the Overall Story, not for parts of the Story.
>> The Story should be estimated as a whole. Points for what a tester feels he needs plus what a developer feels he needs should not be given. Both should estimate the complete Story.
See lessWho knows most about the progress towards a business objective or a release?
A. The Product Owner. This is a task of the Product Owner, as she is the Voice of the Customer.
A. The Product Owner.
This is a task of the Product Owner, as she is the Voice of the Customer.
See lessWhat is the most likely reason that the Team did not meet the Sprint objectives?
C. The Team did not plan the Sprint effectively. >> The Development Team likely did not estimate the Backlog Items well and did not plan the work well. A 2-day absence should not lead to not meeting Sprint Objectives, especially not if that was at the beginning of the Sprint.
C. The Team did not plan the Sprint effectively.
>> The Development Team likely did not estimate the Backlog Items well and did not plan the work well. A 2-day absence should not lead to not meeting Sprint Objectives, especially not if that was at the beginning of the Sprint.
See lessWhat is expected of you when this happens?
C. Help the co-workers in the column with the bottleneck. >> When the WIP limit is reached, this is not a sign to relax, but rather a sign that there is a bottleneck. This bottleneck should be addressed. The team has to help the coworkers that are the reason why the WIP limit is reached.
C. Help the co-workers in the column with the bottleneck.
>> When the WIP limit is reached, this is not a sign to relax, but rather a sign that there is a bottleneck. This bottleneck should be addressed. The team has to help the coworkers that are the reason why the WIP limit is reached.
See lessWhose estimate should be used for planning?
D. The Development Team. >> At the end of the day, the only estimate that matters is the one given by the team members working on the story.
D. The Development Team.
>> At the end of the day, the only estimate that matters is the one given by the team members working on the story.
See lessWho is in the best position to conduct such an audit?
B. The Scrum Master. >> One of the Scrum Master's responsibilities is to be the coach of the Team and to ensure that the Team is following the Scrum processes. This allows the Scrum Master to conduct this audit.
B. The Scrum Master.
>> One of the Scrum Master’s responsibilities is to be the coach of the Team and to ensure that the Team is following the Scrum processes. This allows the Scrum Master to conduct this audit.
What is the best way to continue the Scrum rituals in this situation?
C. The Scrum Master should take over and cover for the Product Owner. >> In a well-planned Sprint, the Scrum Master can take over from the Product Owner for a little while. If the Product Backlog Items are ordered well, it should be self-evident what should be done next. If necessary, the ScruRead more
C. The Scrum Master should take over and cover for the Product Owner.
>> In a well-planned Sprint, the Scrum Master can take over from the Product Owner for a little while. If the Product Backlog Items are ordered well, it should be self-evident what should be done next. If necessary, the Scrum Master can take over this task.
See lessWhat is the definition of Velocity of a Team?
C. The number of Story Points a Team can finish in 1 Sprint. >> The velocity is the number of units of work completed in a certain interval.
C. The number of Story Points a Team can finish in 1 Sprint.
>> The velocity is the number of units of work completed in a certain interval.
See lessShould the duration be increased?
B. Yes, because past Sprint performance is a good reason to change. >> The Scrum Master gives a valid argument, based on a good amount of earlier work, that the Sprint duration should be changed.
B. Yes, because past Sprint performance is a good reason to change.
>> The Scrum Master gives a valid argument, based on a good amount of earlier work, that the Sprint duration should be changed.
See lessWhich contract type is adaptive and therefore fits well with the Scrum way of working?
A. The contract type “Time & means or fixed unit”. ->>"Time & means or fixed unit"– this is our preferred type of contract, which is compatible with the adaptive nature of the project." "Fixed Price– even though most customers like fixed price, fixed scope contracts and even some of thRead more
A. The contract type “Time & means or fixed unit”.
->>”Time & means or fixed unit”– this is our preferred type of contract, which is compatible with the adaptive nature of the project.” “Fixed Price– even though most customers like fixed price, fixed scope contracts and even some of them are required by law to have only fixed-price contracts, it is not really Agile.” So adaptiveness is the key value. It is hard to be adaptive when the project price is fixed. This is why “Time & means or fixed unit” clearly fits easier with Agile and Scrum.
See less