You follow the progress of the Sprint on a burn-down chart. What does it mean if the line of real progress is above the line of planned progress?
a) Too many User Stories have been planned for this Sprint.
b) Too few User Stories have been planned for this Sprint.
c) The progress achieved so far is slower than the one planned.
d) The progress achieved so far is faster than the one planned.
c) If the line of real progress is above the line of planned progress, it means the progress achieved so far is slower than the one planned.
c) If the line of real progress is above the line of planned progress, it means the progress achieved so far is slower than the one planned.