A Scrum Team selects a Product Backlog Item (PBI) for the Sprint Backlog.
What must the Development Team do to finish the Product Backlog Item it selects?
A. As much as can be done in the Sprint before the deadline.
B. As much as is required to satisfy the Definition of Done.
C. Analyze, design, program, test and document the Product Backlog Item.
B. As much as is required to satisfy the Definition of Done. The Definition of Done is guiding in what needs to be done before a Backlog Item is finished.
B. As much as is required to satisfy the Definition of Done.
The Definition of Done is guiding in what needs to be done before a Backlog Item is finished.