In release management, the interrelations of the individual planning levels is important. Which of the following is not correct?
a) The release consists of at least one sprint
b) In projects, which consist of less than 6 sprints, release planning is generally not
required
c) A task can be completed within one sprint
d) A task is attributed to a user story
b) In projects, which consist of less than 6 sprints, release planning is generally not required.
b) In projects, which consist of less than 6 sprints, release planning is generally not required.
See less