There are different ways to determine the velocity (development speed). Which of the following statements is true?
a) If a release plan has to be created before the first sprint, the development speed
can be estimated with the help of the team
b) The development speed is independent of the size of the development team
c) Development speed should increase by at least 20% from Sprint to Sprint
d) The development speed will be set in the sprint retrospective for the following sprint
a) If a release plan has to be created before the first sprint, the development speed can be estimated with the help of the team.
a) If a release plan has to be created before the first sprint, the development speed can be estimated with the help of the team.