a) A sprint lasts on average 2-4 days
b) Requirements are transferred from the Product Backlog into the Sprint Backlog
c) The Product Owner monitors the Daily Scrums
d) Should there be conflict, the Scrum Mediation team is activated
MorganEnlightened
b) Requirements are transferred from the Product Backlog into the Sprint Backlog.
b) Requirements are transferred from the Product Backlog into the Sprint Backlog.
See less