a) In the Daily Scrum improvement measures are implemented
b) A Sprint last for a maximum of 30 days
c) Every sprint generates its own and independent product increment
d) Goal of the Sprint Planning is the identification of improvement measures
MorganEnlightened
b) A Sprint last for a maximum of 30 days
b) A Sprint last for a maximum of 30 days