A. The team should plan to work a small amount of overtime regularly throughout the project
B. The team should expect to work longer hours towards the end of the sprint (timebox), in order to deliver all that was committed to
C. The team should strive for a sustainable pace and a normal working week
D. The team will “burn out” if they have to work overtime for more than two sprints
(timeboxes, iterations) in a row
MorganEnlightened
C. The team should strive for a sustainable pace and a normal working week.
C. The team should strive for a sustainable pace and a normal working week.
See less