There are different ways to determine the velocity (development speed). Which of the following statements is true? a) If a release plan has to be created before the first sprint, the development speed can be estimated with the help of the ...
ExamList Latest Questions
a) In the figurative sense of traditional project management methods, the Scrum Master takes the role of the project lead b) For an efficiently working team, the Scrum Master should have authority with regards to the team’s work organization c) ...
The prioritization of the Product Backlog by the Product Owner is an important tool to steer the project. When prioritizing, the following should be considered: a) that requirements with high risk and great added value should be implemented as soon as ...
a) The development speed report can assist in directly extrapolating to the story points of the next sprint b) The Velocity Chart shows the development speed of the next sprint c) The x-axis depicts the individual sprints d) The ideal ...
a) The management should advocate a structural change in the company b) Management can influence the work of the development team in the first sprint c) The Product Owner also assumes the role of Scrum Master in the first project
a) Which activities have I completed since the last Daily? b) What am I planning to work on before the next Daily? c) Are there any impediments that may block my activities? d) Which requirements from the Product Backlog are ...
In release management, the interrelations of the individual planning levels is important. Which of the following is not correct? a) The release consists of at least one sprint b) In projects, which consist of less than 6 sprints, release planning is ...
a) Detailed questions about requirements are clarified in Scrum by the development the team directly with customers without the involvement of the product owner b) A development team should have more than 20 members c) The development team should be ...
The Sprint Backlog can be structured as time management system, in order to track the sprint’s progress. In doing so, which of the following characteristics does not apply to the Sprint Backlog? a) It contains the requirements and tasks to which ...
a) Splitting stories is not part of the refinement and should not claim the capacity of the development team b) The splitting of stories is part of the five 5 Scrum events c) The subdivisions and the associated depth of ...