A. Appointing a single point of contact for communication across locations B. Co-locating the entire team for a release planning session C. Establish a clear audit trail for all communication on the project D. Introduce additional sign-offs on the project ...
ExamList Latest Questions
A team is transitioning into Scrum. They already had a role called Project coordinator, who facilitates interactions, removes roadblocks and acts as the process coach of the team. What should this role be called post-transition? A. Project coordinator B. Project manager C. ...
A. One to three hours B. Three to six hours C. Six to twelve hours D. Fifteen hours
Scrum Teams should normalize their estimates (by using the same reference scale), so that management can compare team velocities and use them as a coordinated productivity measure. [A] True [B] False
What action will the Development Team take when it is discovered that new work is required to complete the agreed-upon task(s)? [A] The Development Team adds the new work to the Sprint Backlog. [B] The Development Team adds the new work ...
[A] The Scrum Master has no authority over Scrum team members, but that authority is granted by the team. [B] If needed, the Scrum Master will work with the Product Owner to make sure the Product Backlog is in good ...
[A] Refinement is a part-time activity during a Sprint between the Product Owner and the Development Team. [B] Refinement is a full-time activity during a Sprint for the Scrum Team. [C] Refinement is a part-time activity during a Sprint between ...
[A] The team is able to complete the project according to the planning after the date and cost are committed to the Product Owner. [B] The team has all the skills on board, needed to accept collective ownership for the ...
One of the benefits from Scrum is that the Development Team doesn’t have to write detailed specifications anymore. [A] True [B] False
[A] Members of Development Teams are exchanged frequently to promote continuous learning and cross-functionality. [B] The Development Team provides input for the Sprint Planning [C] The Development Team may re-negotiate with the Product owner the work needed to deliver the ...