A. Automatically included in the work of the project
B. Automatically excluded and left until a later project or increment
C. Assessed for importance and, if sufficiently important to the business, including in the project, displacing less important requirements
D. Put on the backlog for consideration by the wider group of stakeholders after the project has been completed
MorganEnlightened
C. Assessed for importance and, if sufficiently important to the business, including in the project, displacing less important requirements.
C. Assessed for importance and, if sufficiently important to the business, including in the project, displacing less important requirements.