A Scrum Team thought it a good practice to clearly define a checklist of items that must be completed before calling a story “completed”.
What artifact are they likely to use for this?
A. Burn-Down Chart
B. Definition of Done
C. Product Backlog
D. Sprint Backlog
B. Definition of Done. Definition of Done is a well understood and clearly documented definition of items that must be established to mark a story (or iteration or project) to be done.
B. Definition of Done.
Definition of Done is a well understood and clearly documented definition of items that must be established to mark a story (or iteration or project) to be done.