While reviewing a bar style release Burn-Down chart, a newly appointed Scrum Master observed that the bottom of the bar had moved above the horizontal axis between Sprint 3 and 4.
What happened in Sprint 3?
A. The Development Team finished less than the allocated stories.
B. The Development Team finished more than the allocated stories.
C. Work got added to the Product Backlog.
D. Work got removed from the Product Backlog.
D. Work got removed from the Product Backlog. In a release level Burn-Down bar chart, work getting removed from the Product Backlog can be indicated by moving the bottom of the bar up. This shows that the new 0- axis is at the same level of the bar. When that point is reached, no more work needs toRead more
D. Work got removed from the Product Backlog.
In a release level Burn-Down bar chart, work getting removed from the Product Backlog can be indicated by moving the bottom of the bar up. This shows that the new 0- axis is at the same level of the bar. When that point is reached, no more work needs to be done, even though the graph will not say 0 yet.