Near the end of a Sprint, the Development Team realizes that they will not be able to complete the stories they had committed to.
What is the best course of action for the Development Team?
A. Add resources and team members to meet the goals of the current Sprint.
B. Ask the Product Owner to decide which stories can be delayed until the next Sprint.
C. Decide on a new Definition of Done for the Sprint Backlog Items.
B. Ask the Product Owner to decide which stories can be delayed until the next Sprint. The Product Owner should decide which items have the most value and should be done first in this Sprint.
B. Ask the Product Owner to decide which stories can be delayed until the next Sprint.
The Product Owner should decide which items have the most value and should be done first in this Sprint.