The Product Owner is going on a three-week vacation. The Team should be closing the current Sprint and starting a new Sprint at the end of the first week of the Product Owner’s vacation.
What is the best way to continue the Scrum rituals in this situation?
A. Each Scrum Team should ideally have two Product Owners to provide cover.
B. The Product Owner should be requested to delay his vacation by a week.
C. The Scrum Master should take over and cover for the Product Owner.
C. The Scrum Master should take over and cover for the Product Owner. >> In a well-planned Sprint, the Scrum Master can take over from the Product Owner for a little while. If the Product Backlog Items are ordered well, it should be self-evident what should be done next. If necessary, the ScruRead more
C. The Scrum Master should take over and cover for the Product Owner.
>> In a well-planned Sprint, the Scrum Master can take over from the Product Owner for a little while. If the Product Backlog Items are ordered well, it should be self-evident what should be done next. If necessary, the Scrum Master can take over this task.
See less