A. It removes the need to create any other reports for management
B. It continuously communicates progress within the team and to other stakeholders
C. It allows the Project Manager to allocate tasks to specific team members
D. It is restrictive, as it does not allow the team to innovate and change
MorganEnlightened
B. It continuously communicates progress within the team and to other stakeholders.
B. It continuously communicates progress within the team and to other stakeholders.