In order to better track the progress of the project, it is useful to define further metrics. Which of the following metrics can be useful? 1) Number of impediments 2) Planned vs. actual project status 3) Results of individual teams 4) Velocity
a) all mentioned
b) Only 1 and 2
c) all except 1
d) Only 2 and 4
a) all mentioned
a) all mentioned