a) Stakeholders may also be invited to the Sprint Review, in order to give unfiltered
feedback to the team
b) The meeting takes place at the end of the Sprint and lasts for a maximum of 2
hours
c) The Scrum Master invites to the Sprint Review
d) The aim of the Sprint Review is the assessment and approval of the working results of the sprint
MorganEnlightened
b) The meeting takes place at the end of the Sprint and lasts for a maximum of 2 hours
b) The meeting takes place at the end of the Sprint and lasts for a maximum of 2 hours