A Scrum Team estimates a Story using the Planning Poker technique. The Team decides to allocate 5 Story Points to a Story because the developers estimated 2 points and the testers estimated 3 points.
Which statement is true regarding this scenario?
A. Points are assigned by the Scrum Master, not by the Development Team.
B. Points are assigned for the overall Story, not for parts of the Story.
C. Points are never estimated, but always determined beforehand.
D. The Development Team also needs to ask the Product Owner about the estimate.
B. Points are assigned for the Overall Story, not for parts of the Story. >> The Story should be estimated as a whole. Points for what a tester feels he needs plus what a developer feels he needs should not be given. Both should estimate the complete Story.
B. Points are assigned for the Overall Story, not for parts of the Story.
>> The Story should be estimated as a whole. Points for what a tester feels he needs plus what a developer feels he needs should not be given. Both should estimate the complete Story.