A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint.
Who can best prepare this report?
A. The Product Owner
B. The Scrum Master
C. The Development Team
D. This type of report should not be prepared.
B. The Scrum Master. >> The Scrum Master should indeed get the impediments of the Development Team out of the way and is thus in the best position to write this report.
B. The Scrum Master.
>> The Scrum Master should indeed get the impediments of the Development Team out of the way and is thus in the best position to write this report.