A Product Owner wants a story to be completed in two days. The Development Team member working on the Story reckons it will take five days. The Scrum Master feels it should take three days. A subject matter expert, who has worked on similar Stories in the past, thinks it should be at most a one-day effort.
Whose estimate should be used for planning?
A. The Product Owner’s
B. The Scrum Master’s
C. The Subject Matter Expert
D. The Development Team
D. The Development Team. >> At the end of the day, the only estimate that matters is the one given by the team members working on the story.
D. The Development Team.
>> At the end of the day, the only estimate that matters is the one given by the team members working on the story.