An often used best practice is to define User Stories according to the acronym ‘INVEST’. The ‘S’ of ‘INVEST’ means Small. Regarding the User Story in a Sprint, what must be small? A. the number of Sprints needed to realize the User ...
ExamList Latest Questions
User Stories in the Product Backlog should correspond to the INVEST acronym. Among other things, they should be independent of each other. What is the best explanation with which you would try to convince a new Product Owner of the ...
A. Iterations (timeboxes) should always be 30 days B. The team determines iteration (timebox) length by dividing the total number of story points by the average velocity of the team C. Iterations (timeboxes) should always be two weeks D. The ...
a) Awareness, Desire, Ability, Promotion, Transfer. b) Awareness, Direct, Ability, Promotion, Transfer. c) Awareness, Desire, Affinity, Promotion, Transfer. d) Awareness, Desire, Ability, Poker, Transfer.
Betty Smith is an avid golfer. While teeing off at her golf club recently, she sliced her shot and hit her golfing partner, Susan Jones, in the face causing Susan to suffer a laceration, severe pain, and temporary loss of ...
A. The Daily Scrum helps the Scrum Master to update the burn-down chart. B. The Daily Scrum gives the Development Team insight into their progress and their issues. C. The Daily Scrum lets the Product Owner review the progress of ...
(A) Premium auditing is the verification of premium information included on an insurer’s financial statements. (B) Premium auditing is a methodical examination of the insured’s operations, records, and books of account to determine the actual exposure units and premiums for ...
(A) Workers Compensation is governed by a system of laws that vary from state to state. (B) A federal system that assures uniformity across the country governs workers’ compensation insurance. (C) Workers Compensation is an exclusive remedy that effectively shields ...
a. Subrogation b. Causa Proxima c. Insurable interest d. Contribution e. Mitigation of loss
Near the end of a Sprint, the Development Team realizes that they will not be able to complete the stories they had committed to. What is the best course of action for the Development Team? A. Add resources and team members to ...